Planning your first major outdoor living project can feel overwhelming. How long does it take? What happens at each step? Who handles permits? How do I know the contractor is on schedule? This guide walks you through the complete process of an outdoor living project with VistaScapes & Design — from your first call to the day you’re using your new outdoor space.

Step 1: Free On-Site Consultation (Week 1)

Every project starts with a free on-site consultation at your property. Here’s what happens:

  • We walk the yard together and assess your space — grade, drainage, sun exposure, access points, existing utilities
  • We listen to your vision — what you want the space to do, how you’ll use it, what you’ve seen that you love
  • We discuss the realistic scope given your yard’s constraints and your budget range
  • We show you project photos from similar Broken Arrow and Tulsa builds
  • We leave you with a rough concept of what’s possible and a ballpark investment range

The consultation typically takes 60-90 minutes. There’s no pressure and no commitment — we just want to understand your project fully before putting together a proposal.

Step 2: Design Development and Proposal (Week 2-3)

After the consultation, we develop:

  • A design concept showing your outdoor space layout — patio shape, structure placement, kitchen orientation, fire feature location
  • Material specifications — exact stone type, countertop material, structure framing, roofing
  • A detailed written proposal with itemized scope, timeline, and total investment
  • Any design revisions needed based on your feedback

We present the proposal at a second meeting — either at your home or virtually. We walk through every line item so you understand exactly what you’re getting and why.

Step 3: Contract Signing and Scheduling

When you’re ready to move forward, we sign the contract and collect the deposit. At that point:

  • We place orders for any custom or long-lead materials (specialty stone, special-order appliances)
  • We begin the permit application process (typically 1-3 weeks for approval in Broken Arrow and Tulsa)
  • We schedule your project into our production calendar and assign a dedicated project manager
  • We communicate your expected start date and estimated completion window

Step 4: Pre-Construction Site Prep

Before main construction begins, we:

  • Locate all underground utilities (Oklahoma One-Call — mandatory before any excavation)
  • Mark the patio and structure footprint so you can visualize the layout before we dig
  • Discuss staging areas for materials and equipment access
  • Confirm all permits are in hand

Step 5: Construction (1-6 Weeks Depending on Scope)

Construction phases typically follow this sequence:

  • Excavation and base work — digging to depth, compacting crushed stone base
  • Underground utility rough-in — gas, electrical conduit, and water supply lines placed in the ground before paving
  • Slab or footing pours — concrete footings for structure posts, kitchen base slab
  • Structure framing — posts, beams, and roof framing for covered patios or pavilions
  • Kitchen cabinet construction — block or stud framing for the outdoor kitchen
  • Patio surface installation — stone or paver setting on the prepared base
  • Countertop installation — granite, quartzite, or concrete tops set in place
  • Appliance installation — grill, refrigerator, and other appliances set and connected
  • Electrical and gas final connections — permitted finishes by licensed trades
  • Finish work — trim, caulking, coping, edging, final details

Step 6: Final Inspection and Walkthrough

When construction is complete:

  • The city inspector signs off on permitted work (electrical, gas, and structural)
  • We do a final walkthrough with you — testing every appliance, lighting fixture, and gas connection
  • We explain care and maintenance for your specific materials and appliances
  • We collect the final payment at project completion
  • You get a full package of warranty information, maintenance guides, and permit close-out documents

Typical Timeline Summary

  • Consultation to proposal: 1-2 weeks
  • Contract to permit approval: 2-4 weeks
  • Simple patio installation: 3-7 days
  • Outdoor kitchen with covered structure: 3-6 weeks
  • Full outdoor living project (patio + kitchen + structure + fire feature): 5-10 weeks